PUBLIC WORKS COMMITTEE
MEETING AGENDA
EDELWEISS CONDOMINIUMS CONFERENCE ROOM
TAOS SKI VALLEY, NEW MEXICO
2:00 P.M., THURSDAY, MARCH 15, 2007
I. CALL TO ORDER & ROLL CALL
II. APPROVAL OF THE AGENDA
III. APPROVAL OF THE NOTES OF THE SEPTEMBER 20, 2006 MEETING
IV. NEW BUSINESS
A. Discussion Regarding Water and Sewer Rates for FY 2007-08
B. Discussion Regarding Revisions to Sewer Line Extension Map
IV. OLD BUSINESS
V. MISCELLANEOUS
VI. ANNOUNCEMENT OF THE DATE, TIME & PLACE OF THE NEXT MEETING OF THE VILLAGE COUNCIL
Village of Taos Ski Valley
Wastewater Treatment Plant Improvements
Outline for Public Meeting, January 15, 2004
I. INTRODUCTION AND OVERVIEW
● Review of Performance Evaluation Study
● Funding Alternatives
● Project Schedule
● Next Steps
II. REVIEW OF PERFORMANCE EVALUATION STUDY (Preliminary Engineering Report- PER)
● Plant Performance Study Objectives
Analyze treatment plant data and growth data
Evaluate performance and capacity of unit processes
Develop solutions to meet future needs
Estimate costs for solutions
● Future Flows
● Plant Process Capacity Review
● Needed Plant Improvements
Headworks
Building Rehabilitation
Equipment Rehabilitation
Increased Capacity for Growth
● Alternatives
New Facilities
Upgrade and Improvements
● Costs for Alternatives
● Costs for Recommended Improvements
III. FUNDING ALTERNATIVES
● Rural Development Grant or Loan
● Municipal Bond
● State Revolving Fund (SRF)
IV. PROJECT SCHEDULE - Discussion of Tentative Dates
● SRF Loan Process
Initial Application - Completed
Priority Listing - Completed
Public Hearing # 1 - Completed
Draft PER Submitted and under review
Public Meeting and Forest Service Kickoff Meeting are today
Environmental Information Document (EID) to be completed by 1/31/04
Public Hearing #2 is scheduled for March (focus on EID)
Final PER and EID to be completed in May
NMED review to be completed in summer 2004
Loan process to be completed by end of summer 2004
● Financial Tasks
Review current rates and fees - completed
Special Election to increase sales tax is scheduled for March 2
Pass loan and rate ordinance as required
● Forest Service Permit Amendment
Initial Application - completed
Forest Service project review and environmental assessment bo be completed by summer 2004
Forest Service design review to be completed by winter 2004
Permit amendment issued in fall 2004
● NMED Permits and Review
Water Quality review to be completed by fall 2004
Discharge permit to be completed and issued by spring 2005
● Design
Scheduled to begin in July 2004
Bidding is scheduled for December 2004
● Construction and Start Up
Contract awarded in January 2005
Construction to being in spring 2005 as weather permits
Substantial completion by October 31, 2005
V. CONCLUSION
● Comments
● Next Steps
Completion of EID
Special Election
Public Hearing in March