Staff has developed a phasing plan for community-wide sewer line extensions. Estimated costs of extending sewer lines throughout the Community including Amizette are just over $2,000,000. We have over four miles of sewer line to install with almost 70 manholes according to the plan.


Phase 1- Zap’s Road (Porcupine Road)/Cliffhanger Loop/ Phoenix Switchback


Staff is recommending that this be Phase 1 of the Sewer Line extension project commencing in summer of 2005. There are three smaller sections included with this phase including extensions along Cliffhanger, Phoenix Switchback and Cliffhanger Loop. Currently, there is a 3" sewer line along Porcupine Drive servicing a small number of homes in this area. The 3" line cannot accept solids. Staff recommends upgrading this line to a 6" line allowing for acceptance of solids negating any future use of septic tanks for solid material. There would be three easements needed to complete the Porcupine/Twining section of this phase. This phase also includes additional manholes on the Interceptor Line. This sewer line extension section in depicted in red on the maps.

 

2,370 l.f. x $50.00 per l.f. =                    $118,500

18 manholes x $5,000 per manhole =    $ 90,000

                                                                $208,500

                                                                x 20% (Eng/Contin.)

                                                                $250,200


2,370 l.f./24 lots served = 99 l.f per lot

 

$250,200/24 lots served = $10,425 per lot



phase 2 -Twining Road/Big Horn Hill/Wolf Lane/Coyote Lane/Dolcetto Lane

 

3,240 l.f. x $50.00 per l.f. =                    $162,00

13 manholes x $5,000 per manhole =    $  65,000

                                                                $227,000

                                                                x 20% (Eng/Contin.)

                                                                $272,400


3,240 l.f./31 lots served = 104.1 l.f per lot

 

$272,400/31 lots served = $8,787 per lot


Phase 3- Chipmunk Lane/Kachina Road/Mine Slide Road/Bull of the Woods Road/Snowshoe Trail


Completion of Phase 3 is predicated upon the Village completing Phase 2. There are no known easement needed at this point as the sewer lines will be installed in Village right-of-way. Project could occur in 2005 or 2006 dependent upon funding options.

 

2,970 l.f. x $50.00 per l.f. =                    $148,500

16 manholes x $5,000 per manhole =    $ 80,000

                                                                $228,500

                                                                x 20% (Eng/Contin.)

                                                                $274,200


2,970 l.f./20 lots served = 149 l.f per lot

 

$274,200/20 lots served = $13,710 per lot

 


Phase 4- Amizette Area


This is the final and most costly phase of extending sewer line throughout the community. Work to complete this aspect would most likely not occur for many years.

     

  

7,020 l.f. (forced main) x $50 per l.f. =$351,000

2,460 l.f. (gravity) x $50 per l.f.=         $123,000

4,500 l.f. (interceptor) x $50 per l.f.=   $225,000

23 manholes x $5,000 per manhole =   $115,000

Lift station (estimated)                          $200,000

                                                             $1,014,000

                                                               x 20% (Eng/Contin.)

                                                             $1,216,800


13,980 l.f./68 lots served = 206 l.f per lot

 

$1,216,800/68 lots served = $17,894 per lot

 


Total Costs of Community-Wide Sewer Extension Project Including Amizette - $2,013,600


$2,013,600/143 Total Lots Served = $14,081 per lot


Total Linear Feet- 22,560


22,560/143 Total Lots served = 157 l.f. per lot