Staff has developed a phasing plan for community-wide sewer line extensions. Estimated costs of extending sewer lines throughout the Community including Amizette are just over $2,000,000. We have over four miles of sewer line to install with almost 70 manholes according to the plan.
Phase 1- Zap’s Road (Porcupine Road)/Cliffhanger Loop/ Phoenix Switchback
Staff is recommending that this be Phase 1 of the Sewer Line
extension project commencing in summer of 2005. There are
three smaller sections included with this phase including
extensions along Cliffhanger, Phoenix Switchback and
Cliffhanger Loop. Currently, there is a 3" sewer line along
Porcupine Drive servicing a small number of homes in this area.
The 3" line cannot accept solids. Staff recommends upgrading
this line to a 6" line allowing for acceptance of solids negating
any future use of septic tanks for solid material. There would be
three easements needed to complete the Porcupine/Twining
section of this phase. This phase also includes additional
manholes on the Interceptor Line. This sewer line extension
section in depicted in red on the maps.
2,370 l.f. x $50.00 per l.f. = $118,500
18 manholes x $5,000 per manhole = $ 90,000
$208,500
x 20% (Eng/Contin.)
$250,200
2,370 l.f./24 lots served = 99 l.f per lot
$250,200/24 lots served = $10,425 per lot
phase
2 -Twining Road/Big Horn Hill/Wolf Lane/Coyote
Lane/Dolcetto Lane
3,240 l.f. x $50.00 per l.f. = $162,00
13 manholes x $5,000 per manhole = $ 65,000
$227,000
x 20% (Eng/Contin.)
$272,400
3,240 l.f./31 lots served = 104.1 l.f per lot
$272,400/31 lots served = $8,787 per lot
Completion of Phase 3 is predicated upon the Village completing Phase 2. There are no known
easement needed at this point as the sewer lines will be installed in Village right-of-way. Project
could occur in 2005 or 2006 dependent upon funding options.
2,970 l.f. x $50.00 per l.f. = $148,500
16 manholes x $5,000 per manhole = $ 80,000
$228,500
x 20% (Eng/Contin.)
$274,200
2,970 l.f./20 lots served = 149 l.f per lot
$274,200/20 lots served = $13,710 per lot
This is the final and most costly phase of extending sewer line throughout the community. Work to complete this aspect would most likely not occur for many years.
7,020 l.f. (forced main) x $50 per l.f. =$351,000
2,460 l.f. (gravity) x $50 per l.f.= $123,000
4,500 l.f. (interceptor) x $50 per l.f.= $225,000
23 manholes x $5,000 per manhole = $115,000
Lift station (estimated) $200,000
$1,014,000
x 20% (Eng/Contin.)
$1,216,800
13,980 l.f./68 lots served = 206 l.f per lot
$1,216,800/68 lots served = $17,894 per lot
$2,013,600/143 Total Lots Served = $14,081 per lot
Total Linear Feet- 22,560
22,560/143 Total Lots served = 157 l.f. per lot